While the critical chain may change during the course of project execution,
it does not mean you should reschedule the project.
_____
From: CriticalChain@yahoogroups.com [mailto:CriticalChain@yahoogroups.com]
On Behalf Of sugan685
Sent: Wednesday, July 23, 2008 10:31 PM
To: CriticalChain@yahoogroups.com
Subject: [CriticalChain] CCPM : Re-scheduling is possible??
Dear All,
Does Critical chain must remain constant during the entire project ,
if yes
In case due to buffer penetration new resource conflicts are created &
therefore we need to recompute the critical chain .
I am new to this field . Please guide me.
Regards,
Sugan
[Non-text portions of this message have been removed]