I have, I think it's the most thorough treatment on the subject. Maybe a little short on implementation, but if you want to understand CCPM very well, this...
Todd I ordered it as soon as it was released. I have read it cover to cover. When people ask me what one book to read to get started on CCPM, this is the book...
I received this at the same time as your posting: this comprehensive list covers all TOC and not just project Management but might be worth seeing: A number of...
Here is a great chronology of an implementation... Very instructive. http://pqa.net/ProdServices/ccpm/W05002005.html I don't know who these people are, but...
Wow! Thanks for sharing that Mark. _____ From: CriticalChain@yahoogroups.com [mailto:CriticalChain@yahoogroups.com] On Behalf Of Mark Woeppel Sent: 21 June...
You're welcome!! mark woeppel President & CEO | Pinnacle Strategies 972-491-1333 | 3600 Lowrey Way . Plano . Texas . 75025 www.pinnacle-strategies.com |...
Thanks. I ordered it. Any input on this: https://www.amazon.com/exec/obidos/ASIN/1574441957/qid%3D1119393399/sr%3D11-1/ref%3Dsr%5F11%5F1/102-9813071-5688914...
The two texts you must havea are Larry Leach's book (per the previous thread) and the Kendall/Rollins book, which is much stronger on multi-project management....
Hi Todd, I think the book in the link: "*Project Management in the Fast Lane: Applying the Theory of Constraints*" is a really great book. It is easy to ...
I don't think you'll find that in CCPM - but I could be wrong. mw mark woeppel President & CEO | Pinnacle Strategies 972-491-1333 | 3600 Lowrey Way . Plano ....
Thank you, Mark. You could be right, but I've heard about a combined use of earned value and CCPM, even if I haven't found anything written about it. On the...
Hi, Guys CCPM covers the cost buffer. The second edition is better on tracking, as I figured out how to do it in a way that supports Earned Value Management...
Dynamic Cycle Time = WIP/Throughput Rate Reduction in Cycle Time is the goal by reducing WIP and/or increasing Throughput That help? Todd Hartle ...
David Hendrickson
dhendrickson@...
Jun 22, 2005 7:22 pm
2187
Todd, Any Lean journey strives to minimize waste and increase speed. Increasing speed equates to reducing lead time to your customers. Minimizing waste...
In parallel with Larry, an associate and I have been working on the modeling of Cost Buffers. We think that they will be better than simply connecting to the...
Some links supporting Joe Bradley's view : Following links demonstrate the flaws in Earned Value and represent a solution, "Earned Schedule". Critical chain...
Todd, I used Google to come up with the following: http://en.wikipedia.org/wiki/Little's_law http://www.isixsigma.com/dictionary/Littles_Law-690.htm ...
Little's Law states that `The average number of things in the system is the product of the average rate at which things leave the system and the average time...
Hi, Does anyone have a good reference to material concerning the use of CCPM in the Software Development industry? Either in software product development or in...