I would like to know if anyone has successfully implemented Critical Chain on a Federal Government managed project. My primary interest is in acquisition...
Do you mean government contracts? i.e. if you mean defense contractors, then yes it has been implemented successfully. Dave "Jim Turbok" <jturbok@chesape...
Hi all, As we all knows ChiticalChain project management is based on finding CC and adding buffers. Question: must be resources allocated for buffers or not? ...
Vidmantas Kajokas
vidma@...
Jan 7, 2003 12:13 pm
606
Hi, No resources must be allocated to buffers. In multiprojects, if there are resources shared between projects, first you should find the department or...
Matías Birrell
mbr@...
Jan 7, 2003 12:51 pm
607
s surya, Good moring£¡ What I want to know is what is " "P" numbers of previous projects" ¡¡¡¡Can you give me some hint? thank you! = = = 20:24:00 You...
wanwei
wanwei@...
Jan 7, 2003 12:54 pm
608
I've been working on a computer simulation in trying to find if there is any advantage to using CCBM rather than CPM. Lately, I've been working on the...
... No. ... You don't. A core part of the CCPM solution is to drive out multitasking and pressures to multitask from the environment. All of the CCPM...
... Make sure that in your simulation, you include the effects of due-date behaviors, like Parkinson's Law, that will minimize the expectation of beating (or...
The forwarded essay below my signature block was written by a particularly articulate friend and competitor of mine on a TOC-oriented discussion list. Since...
Hello, Thanks all for answers about resource allocation to buffers, I think, they would help me a lot. But I have another questions regarding CCPM, because in...
Vidmantas Kajokas
vidma@...
Jan 8, 2003 6:34 am
613
With best regards from Wojciech ... From: Daily Dilbert [mailto:dailycomic#2.33139.31333230313435.1@...] Sent: Wednesday, January 08,...
Hi Wanwei... What I meant by "P" was, based on a number of past project, say from my last 30 out of 50 projects, I've found out that activities A,B,D,E,F,G,K &...
b) if in the middle of the project we add some tasks to project, can/must we recalculate this project and all depending projects, because critical chain in...
Vidmantas, Please excuse me if I misunderstand you, my own knowledge is largely theoretical and fairly recent so I hope somebody else will correct me if I've...
... Well, that also means that 20 out of 50 had a different critical chain -- a not insignificant number. Is it possible that the CC for a number of those...
... As someone else suggested, the processes and concepts are "simple," but sometimes, getting around old ways of looking at "the real environment" can make...
My knowledge is largely theoretical at this point as well. But I agree with Ian's response. The subject of planning for the buffers has been discussed here...
McCarthy, Brian
Brian.McCarthy@...
Jan 9, 2003 2:48 am
624
... Good luck, Brian -- Keep us advised on how it goes. ____________________________________________________ Frank Patrick -- Focused Performance ...
Hi there, I've run into some confusion while working on my Critical Chain Simulation. Imagine the situation being 3 tasks in a row, on a non-Critical Chain...
Sorry -- entering the previous message on the web messed up the formatting. Here it is again, should be more readable. Kate Ho asked... ... Tasks are placed in...
Hi! 1. The "as late as possible" (ALAP) aspect of Critical Chain has been seriously abused in my opinion, especially by critics. Thanks for the opportunity to...
Eugene Kania
ekania@...
Jan 17, 2003 3:23 pm
631
Is there a critical chain add on for P3? Any experience with it?...
On 1/17/03 11:53 AM, "Andy Baumer <andybaumer@...>" ... None that I know of, although someone else on the list might. Five or six years ago, after Eli...