Hi Gene, (...) ... in my ... project ... and cannot ... (...) Is that your experience? When CC changes over the execution phase it sounds more as if the...
... Mattias - i agree. a project manager may CHOOSE to reschedule (scope change, disaster, whatever...) but the critical chain does not change otherwise....
Hi! Maybe I am not understanding where you are coming from? Let me seek clarity by example. Let's say that for a simple project, you have two main chains...
Yes, worth repeating. Gene Kania ... From: Frank Patrick To: cclist Sent: Tuesday, July 01, 2003 9:51 AM Subject: Re: [CriticalChain] Re: Query on FAQ 3. ... ...
Good, Gene. I was going to jump in with something similar as I feared we were leading up to a case of violent agreement happening between you, Mattias, and...
897
Matías Birrell
mbr@...
Jul 1, 2003 4:41 pm
... feared we ... between you, ... assumptions of someone ;-) (may be mine this time :-) So what I learnt (again) is that focus is to be on buffers not chains,...
Glad you concur, Frank. Gene ... From: Frank Patrick To: cclist Sent: Tuesday, July 01, 2003 11:04 AM Subject: Re: [CriticalChain] Re: Query on FAQ 3. Good,...
Hi, I'm Ivana Burcar from Zagreb, Croatia. I'm working at Univ. of Zagreb Faculty of Civil Engineering, Department for Construction Management and Economics as...
900
Oscar Navarro
onavarro@...
Jul 2, 2003 11:40 pm
I'am Oscar Navarro, a colombian civil engineer, toc practitioner in textile industries, who is looking too for CCPM experiences in construction projects. Thank...
Hi! I have been following almost all your e-mail but, this is the first time I write to the list I hacve a doubt, what role does the capacity buffer plays in...
902
Matías Birrell
mbr@...
Jul 3, 2003 3:10 am
Hola Gustavo, In a multiproject environment the most loaded resource will be chosen as the drum. The program of the drum is used to stagger the release of the...
Hi Jeff, In the CPM total float is time that can be consumed but it won't effect planned final date of project. Free float is time that can be consumed but it...
... The Capacity Buffer, also known as the Synchronization Buffer adds additional time between the use of the Drum/Synchronizing resource across projects in a...
... Float and free float are concepts that are not explicitly used in Critical Chain-based project management. Float is a mathematical outcome of a simple ...
Interesting observation. In our experience, the thing that "goes wrong" on the critical chain is that we cannot always identify the complete project at the...
This is my advice (and I just gave it again not 30 minutes ago to a real project). If the inserted tasks are small as a percentage of the overall program then...
I concur with Dave. Depending on how early in the project the CC schedule is created, there may be quite a bit of work to be added. Certainly the schedule is...
Hi I have just joined the Group and noticed that there is an interest from a couple of existing members on the application of cricital chain in construction. I...
913
Christian Walenta
walenta@...
Jul 20, 2003 9:04 pm
I will be out of the office starting July 15, 2003 and will not return until July 21, 2003. I will respond to your mail upon return after 7/21. In urgent...
Hi Nicholas I would look forward to news about the use of CCPM in the building Industry. I did at one time try to get in touch with the project managers at...
i´m trying to find informatíon of Critical Chain about Construction, but i don´t find anything. If i find something i promise that i send you an e-mail. I...
I too look forward to hearing about your experiences with this type of application. Regards, Tamara Sutton Walbridge Aldinger...
917
Oscar Navarro
onavarro@...
Jul 22, 2003 4:22 am
Hi Nicholas It would be wonderful to have some information about how it is going the project, and specially how have you applied CC concepts, and what software...
I will be out of the office starting 07/19/2003 and will not return until 07/28/2003. I am on vacation 7/20-7/27. I will be on program travel 7/28-7/30....
Hi Here is the report on the our progress so far with our UK Department of Trade and Industry's funded project Project Overview Objective - to pilot the use of...
920
Oscar Navarro
onavarro@...
Jul 24, 2003 4:16 am
Hi Nicholas Thankyou for your contribution to CC appication in construction. First question, is it possible to have some Pro Chain demo or is it necessary to...