In what could turn out to be a major boost to the ongoing work of Reliance Metro One, hurdles in the construction of a railway over bridge (RoB) have been...
MUMBAI: In a bid to reduce the Rs 9,000 crore viability gap funding (VGF) for the Metro rail's third line from Colaba to Bandra, the Mumbai Metropolitan Region...
State gets letter from Finance Ministry confirming grant of Rs 1,532 cr as viability gap fund for project (From Mumbai Mirror) The state government on Monday...
(from Times of India) MUMBAI: Mumbai Metro One Private Ltd, the special purpose vehicle created to build the metro along Versova-Andheri-Ghatkopar corridor is...
*** Please always include a subject line with your message *** - Vivek Mumbai Metro Railway is an historicla decision of the maharashtra Govt. The first phase...
Hi all, from news articles i see that there is 32 kms of underground component in the 145.6 kms total length of metro proposed for all 3 phases. My question is...
Mumbai Metro trains will be equipped with black boxes, in all the passenger coaches and the motorman's cabin. This will be a first in India as neither of the...
Just a reminder to all the readers, the BRT as a concept has already being implemented in Pune City. It was the first BRT corridor in India and its sucessfully...
Hello, Some members here already know me, but a majority do not, hence this post. I am Akshay Marathe, currently doing engineering. I stay at Borivali. I am a ...
MUMBAI: The first metro rail corridor project in the city is beginning to move forward with a Chinese company bagging the Rs 604 crore contract to supply 16...
This is what appeared on the front page of the TOI today. Mumbai: The centre will fund the `viability gap' for the Mumbai metro project, Union urban...
(from Times of India) MUMBAI: The Mumbai International Airport Limited (MIAL) has suggested the Maharashtra government to extend the proposed metro line from...
Hi All, Sorry, I didnt post this earlier. MUMBAI: A 60-tonne piling rig which was being used in the ambitious Versova-Andheri-Ghatkopar elevated corridor...
Hi Folks, I had the opportunity to travel on the Andheri-Kurla road twice in the last week. Here is what I observed: 1) Metro construction work is in progress...
I wish to get some information about the Calcutta Metro Are the Rakes and rolling stock of the Calcutta Metro completely designed and made in India? Was ICF...
Hi Folks, I have just uploaded a few pics of the Metro construction site at the Western Express Highway junction/Andheri Kurla Road - Andheri East. The photos...
CM gives green signal to form the Mumbai Metro Rail Corporation; Delhi Metro appointed as consultants ... (from mumbai mirror) In a major development that is...
MUMBAI: Vehicles plying between Chakala and Saki Naka and on JP Road between Versova and SV Road will not be able to use a nine-metre passage in the middle of...
MUMBAI: With the civil work on the first line of the Mumbai metro rail project having begun this week, officials are optimistic that the approximately...
The Mumbai Metro One website seems to be taken down for maintenance/update. http://www.mumbaimetro1.com/ This is the message that is displayed: "Welcome to...
* Another stumbling block for the much delayed Metro? * The on going construction work on the metro railway between Versova- Andheri-Ghatkopar received a major...
Hi All - I'd appreciate if someone can please explain the need for a monorail from Mantralaya to CS Intnl. Airport, when there's already a metro being planned...
Hi Folks, After a long wait, work on the Versova-Andheri-Ghatkopar section of the Mumbai Metro rail project began on Friday. After a bhoomi puja, workers of...
(from mumbai mirror) Thursday, December 13, 2007 Construction work on the Mumbai Metro Rail Project will begin within a week, Mumbai Metropolitan Region...
MUMBAI: Malabar Hill in south Mumbai could well be connected via monorail with Wadala and Bandra-Kurla Complex in two years. Chief minister Vilasrao Deshmukh...