Hi, Does anyone have an insight into the 3rd party services offered in the Philippines. This is for typical office recovery (PC, phone, desk, connectivity...
I have a team going offsite to our recovery provider to attempt to test the recovery of a few servers and VM(s). I am looking for a test plan to use a...
Hi J I have a template we have used many times very successfully. In our instance, we have many testers, and if you are prepared to recreate the document as a...
Hello, This email message is a notification to let you know that a file has been uploaded to the Files area of the discussbusinesscontinuity group. File...
discussbusinesscontin...
Dec 10, 2008 12:15 pm
6060
The company I work for was looking at using Perimeter Technology for relocating our servers, but a friend of mine in the auditing business says they have...
First, to answer your question - I'm not familiar with Perimeter Technology. I actually visited a commercial hotsite that did not have a redundant power...
Our company has just merged with another larger company of the same type. We are a chain of retail/wholesale auto parts stores. I have been asked to determine...
Good Morning Bill That is a difficult problem. First, I suggest conducting a BIA to determine which applications directly impact/generate revenue, to include...
I agree with Bob Cohen on where to start, but you may want to have the requestor of the downtime figures explain more about what they are looking for. Being...
You need to do a Business Impact Analysis for the systems at that location. Â First you need to determine what applications run from there, then find out from...
Adolpho - After being though several fires in my time, you would be better off having your IT guys carry those tapes around in the trunk of their car in a...
There are many solutions to datacenters and backups. The number one point it tht the backups must be kepT offiste. Commercial Storage companies charge by the...
Thank you all for your responses to my request for help on this. Your responses were great and extremely helpful. Is anyone else in disbelief that we are...
Michael - I hope you adding content to the thread and not my comment. You are corrent, the best idea is to keep it off site and i believe John was relying...
I read BSI 25999-1 and BSI 25999-2. I found them both lacking in everything but price. For my money, NFPA 1600 (and variations on that theme) do a better...
John I completely agree with you. If ASIS is going through this (in my opinion) unnecessary effort because they feel NFPA isn't auditable, seems to me their...
What is it with this "one size fits all" mentality we are developing? Like the organisations, and sub sections within these organisations, that we service,...
A few questions I'd like to pose to the forum based on what others think about the flurry of Standards being developed. 1 .. Will BCM become a better value...
Hi Howard. Comments below. A few questions I'd like to pose to the forum based on what others think about the flurry of Standards being developed. 1 .. Will...
Rather than a point by point response, I'd like to share my 2 cents on the subject of BCP standards both as an auditor and as a practitioner. First of all,...
Hi Peter, I was the only one copied, so I'm forwarding it with your good comments and some of my own of course. I think there's a difference of opinion on what...
I wanted to pose a basic but important question to the group. What is the best way to arrive at an RPO (recovery point Objective) for an application. Based on...
The businesses must determine the maximum amout of data loss they can accept. In a shared data environment, the "worst case" drives the rest. Having written...
John: Isn't the real job to collect all the data, understand the issues and then present to Sr Management? SR management may have started out with a set of...
Its a usual problem with most users where they think they can't afford to loose any data (even if all they work on is management report/ MI related work).. I...
I'm in agreement with both John and Howard. I think they are saying similar things in different ways (the ever present difficulty interpreting the written...
Most business managers first think that they must have an RPO of point-of- interruption, but quickly change their minds when they see the associated costs. In...
Agreed. Â Normal SOP is for the planner to present the planner's opinion with options for mgt. Â I got the impression this was not acceptable in this...
... Not necessarily. If the standard is a good one, then it will improve overall BCP efforts. However, just because something is a standard doesn't make it a...