I think coming up with measurements and then putting it in radar diagram (I've never heard of Kiveat style diagram. Â Radar is what is used in Excel) Â rocks...
15789
David Anderson
netherby_uk
Jul 13, 2012 5:06 pm
It was Rich Turner that told me these are known as Kiveat diagrams when used in multi-dimensional risk assessment. If Excel calls them "radar" charts that is...
15790
David Anderson
netherby_uk
Jul 13, 2012 5:08 pm
Work = work items, i.e. customer demand...
15791
Tony Lew
sankwon
Jul 13, 2012 7:46 pm
I'm not sure if they can do multiple scales in Excel but it might make sense to standarize the scales across all dimensions for simplicity anyway. You could...
15792
David Anderson
netherby_uk
Jul 13, 2012 8:07 pm
I think this is very dangerous. I want the scales to qualitative in nature and use taxonomies. I fear that the graphing tool will dictate the solution and it...
15793
iwbipny
Jul 13, 2012 8:46 pm
Good points made about both the questionable desirability of reaching a certain depth and the difference between acknowledging potential misuse from ignoring...
15794
Tony Lew
sankwon
Jul 13, 2012 10:43 pm
For 3 kanban kata, instead of 1, 2, 3, you. Have 1, 3, 7. If there are more than 7 things to track, have distribute the weight evenly. So if 14 things, each...
15795
dmhwhite
Jul 14, 2012 3:38 pm
I think what has been discovered is a new way to visualize kanban maturity. Hats off to the #klrat group that acknowledged parallel development/growth of...
15796
David Anderson
netherby_uk
Jul 14, 2012 8:28 pm
Tony, I accept that we can even up the scales on the axes. I am very afraid of people calculating "overall scores." I am not convinced this is a useful idea...
15797
David Anderson
netherby_uk
Jul 14, 2012 8:59 pm
Dave, Wise words! As we've learned over the last 5 years, gently does it. Now we have this concept and tool we need to gather stories of their usage before we...
15798
Karl Scotland
kjscotland
Jul 16, 2012 12:20 pm
Not having been able to attend KLRAT, I'm wondering whether the risk to innovation was discussed at all? Could the definition of steps in each scale lead to...
15799
David Anderson
netherby_uk
Jul 16, 2012 10:55 pm
Karl, The ticks on each axis were not discussed at all at KLRAT, there wasn't time. What I presented last week is my own work building on the KLRAT work, and...
15800
Håkan Forss
hakan_forss
Jul 16, 2012 11:24 pm
Karl, Yes we had a short discussion in the session of the danger of making the steps and/or scales explicit. When I first drew the spider chart I added tick...
15801
Janice Linden-Reed
JLinden
Jul 18, 2012 1:07 am
Some kiviat diagrams have been posted on the Limited WIP Society site here: http://limitedwipsociety.ning.com/photo/albums/kiviat-diagrams-depth-of-kanban It...
15802
Manuel Mazan
manuelmazan
Jul 18, 2012 4:35 am
Hello there, Within my organization I have taken Kanban to software development, HR, operations and now I´m facing the tough one: project portfolio...
15803
Mike Burrows
asplake
Jul 18, 2012 8:34 am
HI Manuel, A traditional approach (not in itself a bad one) would be to visualise committed effort by month or by week in a column chart. That should give you...
15804
Kurt Häusler
kurt.haeusler
Jul 18, 2012 8:41 am
My rough thoughts on the matter are based on how the decision to commit to a project is made. If the decision to commit to a project can be made quickly, on...
15805
Manuel Mazan
manuelmazan
Jul 18, 2012 4:52 pm
Hi Mike Thanks for your reply, perhaps would have been useful to mention that this is a professsional service firm managing a number of software projects for a...
15806
Manuel Mazan
manuelmazan
Jul 18, 2012 5:07 pm
Thanks for the reply Kurt, because this is a professional services team working with external clients we cannot let teams or people pull up projects and start...
15807
Ram Srinivasan
ram_eagle2k
Jul 22, 2012 3:02 pm
I was quite fascinated about how people use the plane game to teach different agile/kanban concepts. http://tastycupcakes.org/2011/07/agile-airplanes/ ...
15808
Christen McLemore
mschrismac
Jul 23, 2012 12:54 pm
Theory of Constraints is actually the purpose of the game but I also use it to demonstrate how the team goes through the process of adjusting WIP, team...
15809
Dave White
dmhwhite
Jul 23, 2012 10:09 pm
I use this game very frequently to primarily teach two principles: - the power of self-organizing teams - teams learn how to maximize value delivery on their...
15810
nijboerl
Jul 24, 2012 10:00 am
I hereby invite you to submit a session for the first Lean Kanban Netherlands conference! The conference will take place October 25 and 26, 2012 in Utrecht. ...
15811
Agustin Villena
agustinvillena
Jul 27, 2012 2:54 pm
Hi! I'm looking for articles, resarch & experiments (games, simulations) that explain this key property of PULL systems : bring predictability to the system...
15812
Dennis
dennisstevens
Jul 27, 2012 7:14 pm
I put together the attached Excel to support management reporting to a client about the status of their projects. We are doing a type of FDD. After an initial...
15813
Ram Srinivasan
ram_eagle2k
Jul 27, 2012 10:29 pm
Hi Dennis, Document is not available. Ram PS: Good to know that you are active here :)...
15814
mdlmmdlm
Jul 27, 2012 10:58 pm
Situation: A company has six teams and three DBAs. They are considering one of the following two options: 1. Assign each DBA to two teams. 2. Create a DBA...
15815
David Anderson
netherby_uk
Jul 27, 2012 11:01 pm
Hi Michael, You need demand analysis for the DBA work from the 6 teams. If the demand is basically steady across all 6 then the 1 DBA for 2 teams should work...
15816
Alan Dayley
dayleyagile
Jul 27, 2012 11:05 pm
My default would be #1 in an effort to create team membership and diverse skills on each team. It is imperfect for a DBA to be a member of two teams, but can...
15817
Jim Benson
ourfounder872
Jul 28, 2012 3:51 pm
Thanks, Will certainly be trying this out. But I'm not sure why Trello doesn't just add the WIP limits as a feature of the system itself, or why we wouldn't be...