OK, sounds good. As you mentioned, work requests can vary greatly in size. When does a kanban team estimate the size of a work request? Is any effort spend on...
523
Landes Eric (CI/AMM1-...
dcma_eric
Feb 1, 2008 1:06 pm
Not sure if this is helpful Martin, but we are trying to estimate each work item using a point system. This is more to help the team understand work in the...
524
Martin Schapendonk
mschapen
Feb 1, 2008 2:50 pm
Eric, thanks for your comments. I'm familiar with the point system and planning poker. But, I know it in relation to Scrum, with fixed sprint length. IMHO,...
525
Corey Ladas
corey_ladas
Feb 1, 2008 8:29 pm
Hello Martin, There are a couple of schools of thought about estimation. Each has its own +/-. 1. Threshold + kanban limit Work-in-process is limited...
526
Chris Matts
chrismatts1968
Feb 1, 2008 9:05 pm
Hi Martin The great thing about the situation you describe is that you know the date that the system needs to be delivered into production on. This falls into ...
527
David J Anderson
netherby_uk
Feb 2, 2008 5:38 am
Adding to the general thread (having read all the posts)... It's worth mentioning that if the request is really urgent the "expedite" (or silver bullet)...
528
Martin Schapendonk
mschapen
Feb 5, 2008 10:04 am
Everybody thanks for the valuable comments. Although it does sound interesting, I won't have the opportunity to visit Dallas in a few weeks time (The...
529
Corey Ladas
corey_ladas
Feb 5, 2008 10:53 pm
Well, I try to be careful about what I'm "in favor of," as I am in favor of whatever makes the most sense for the capability of the team in question. I would...
530
erwilleke
Feb 6, 2008 1:25 pm
All, In the course of reading the latest thread on strict deadlines, I realized how often this group uses terms that carry a great deal of meaning for people...
531
Olav Maassen
kathar_mandel
Feb 6, 2008 1:55 pm
Great initiative....
532
Landes Eric (CI/AMM1-...
dcma_eric
Feb 6, 2008 11:29 pm
Martin, Sorry for the delay in the reply. We use the points combined with our completion dates to right now for a good cycle time estimate (we're mainly using...
533
Aaron Sanders
aremsan
Feb 8, 2008 5:20 pm
Did a Kanban keyword search: http://submissions.agile2008.org/taxonomy/term/588 Keep checking back, and please submit your reviews!...
534
Karl Scotland
kjscotland
Feb 8, 2008 9:47 pm
In putting together a workshop for Agile 2008, I ended up distilling my thoughts down to three key concepts - Kanban, Flow and Cadence - hence KFC. The...
535
Kenji HIRANABE
kenjihiranabe
Feb 11, 2008 11:02 pm
Hello, I have just submitted one Lean session. "Learning Kaizen from Toyota [with Mind Map]" http://submissions.agile2008.org/node/2400 I'm thinking of...
536
David J Anderson
netherby_uk
Feb 15, 2008 5:20 pm
I won't make a habit of using my own group to promote my new business but I know that many folks in this group would be pleased to hear that I've started my...
537
chris.matts@...
chrismatts1968
Feb 15, 2008 6:29 pm
Do you want to add real options to your service offering? ... From: "David J Anderson" <netherby_uk@...> Date: Fri, 15 Feb 2008 17:20:50 ...
538
Kenji HIRANABE
kenjihiranabe
Feb 16, 2008 4:08 am
I submitted a new one. ... New Car Development in Toyota http://submissions.agile2008.org/node/2769 Nobuaki Katayama, the chief engineer of Lexus/SC and IS,...
539
Kenji HIRANABE
kenjihiranabe
Feb 16, 2008 4:13 am
Congratulations, David and Corey! I have been a fan of both of your blogs. -Kenji...
540
Corey Ladas
corey_ladas
Feb 16, 2008 5:03 am
Thank you Kenji. We like your work too! Corey...
541
Corey Ladas
corey_ladas
Feb 16, 2008 5:17 am
Chris, I would say at this point that Real Options is certainly high on the list of things we think are interesting. Perhaps you could take this up with David...
542
chris.matts@...
chrismatts1968
Feb 16, 2008 8:09 am
Oops sorry Thought i had. Damn that reply all button. ... From: Corey Ladas <coreyl@...> Date: Fri, 15 Feb 2008 21:18:02 To:kanbandev@yahoogroups.com ...
543
David J Anderson
netherby_uk
Feb 20, 2008 6:23 pm
I've been very busy with a lot of changes in my life recently, so I've been tardy submitting to Agile 2008. There are only 5 days to go on the submissions....
544
kenjihiranabe
Feb 21, 2008 2:09 pm
Have you seen this video ? http://www.youtube.com/watch?v=zpw8h4OGNxg This is a video of a song "Dear XP", and it includes a lot of kanban boards examples and...
545
Olav Maassen
kathar_mandel
Feb 22, 2008 3:52 pm
Hi all, there is a new session proposal on Kanban submitted for agile 2008 (not by me). http://submissions.agile2008.org/node/3757 with kind regards, Olav...
546
Kenji HIRANABE
kenjihiranabe
Feb 23, 2008 2:53 am
I'm a big fan of GTD! GTD + Kanban... how exciting. -Kenji...
547
Aaron Sanders
aremsan
Feb 23, 2008 11:28 pm
based on the coin flipping, and on the xp game of paper airplane making. http://aaron.sanders.name/lean/simulations-for-throughput-and-pull...
548
David J Anderson
netherby_uk
Feb 24, 2008 3:58 am
Interesting! Thanks for bringing it to our attention. If this is selected, I'll definitely attend. I want to see how others are adapting techniques. The author...
549
Chris Matts
chrismatts1968
Feb 24, 2008 12:26 pm
Dear All Gary Sage, the guy who helped me with the NLP work in Real Options has just submitted a Real Option experience report. ...
550
Chris Matts
chrismatts1968
Feb 24, 2008 1:06 pm
This is freaky. I'm working on a spreadsheet to simulate a very simlar game using dice instead of cards. The aim is to create a huge number of simulations and...
551
Henrik Mårtensson
refactored_m...
Feb 25, 2008 11:08 am
... simlar game ... contraint ... Here is a simulation I did a couple of years ago, when I got tired of rolling dice: ...